Installation overview
How AD-CHIPBOARD Is Installed
Plan the deck and pipe routes together. For a joisted installation, follow the project design and current product instructions:
- 1Confirm heat loss, joist layout, manifold position, pipe circuits and the complete floor build-up.
- 2Prepare the joists and fit insulation between them. Product guidance specifies a maximum 600mm joist spacing; confirm the structural design.
- 3Glue adjoining tongue-and-groove edges and the panel-to-joist contact areas, then screw the panels to the joists as specified.
- 4Fit the 12mm PERT pipe into the routed channels through the foil, following the planned circuit routes.
- 5Connect, fill and pressure-test the circuits before covering the pipe.
- 6Mechanically fix the specified protective deck without damaging the pipe, then fit the approved floor finish.